Oversight to expand capacity of Cusiana - Vasconia system (Cusiana Phase IV Project), with intervention in Puente Guillermo (Santander), Miraflores and Vasconia (Boyacá) stations.
Location and date of execution: Bogota, Departments of Boyaca and Santander, 2018-2019
Client:
Transportadora de Gas Internacional, TGI, Grupo Energía Bogotá.
Scope:
Modify part of the process at gas compression stations of Miraflores (Boyacá), Vasconia (Boyacá) and place an additional compression unit at Puente Guillermo station (Santander). The project envisages civil, mechanical, electrical, instrumentation and control works consisting of:
Connection and commissioning of a new Compression Unit.Expansion of the sound insulation barrier at Puente Guillermo station.
Expansion of shelter at Puente Guillermo station, including the station bridge crane.
Supply and installation of a suction filter and a discharge one at Puente Guillermo and Miraflores stations.
Disassembling of existing Slug Catcher and Assembling of a new Slug Catcher at Vasconia station.
Supply and change of emergency valve train (ESD) and control at Puente Guillermo and Miraflores stations.
Supply and installation of the line and regulation valve at Puente Guillermo station towards Cogua.